Behome Design Concept

Punggol 4 Room HDB Renovation: Part 6 – Day 25 – Carpentry Works

A normal full renovation like this 4 room HDB takes about 6 weeks to complete.  As we approach the end of week 4, all the major works are about to be completed.

Living Room

Punggol 4 Room HDB Day 25 (Carpentry Works)-Living Room- Main door

Punggol 4 Room HDB Day 25 (Carpentry Works) – Living Room – Divider

Punggol 4 Room HDB Day 25 (Carpentry Works) – Living Room – Divider

Punggol 4 Room HDB Day 25 (Carpentry Works) – Living Room – TV console

  • The front door and gate were repainted.
  • Carpentry works: A divider with shelvings and a TV console were installed.
  • Sanitary and kitchen accessories were delivered and placed in the living room.

Kitchen

Punggol 4 Room HDB Day 25 (Carpentry Works) – Kitchen

Punggol 4 Room HDB Day 25 (Carpentry Works) – Kitchen

  • The kitchen cabinet is still in “work in progress” stage.
  • The hood and hob were installed.
  • The “unsightly” pipe will be concealed by the carpentry works.

Common Toilet

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Toilet

  • After some cleaning up, the beautiful tiling works can be seen clearly.

Common Room 1

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 1

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 1

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 1

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 1

  • The white background with pink strips creates a lovely ambience for the princess room.
  • Vinyl flooring was installed.
  • 3 inch timber skirting is used for the whole house.

Common Room 2

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 2

Punggol 4 Room HDB Day 25 (Carpentry Works) Common Room 2

Punggol 4 Room HDB Day 25 (Carpentry Works) – Common Room 3 – Door frame repainted.

  • Painting and flooring works were completed.
  • The old door frames were repainted.

Master Room

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom – Wardrobe

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom – Wardrobe

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom – Wardrobe internal

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom – Blum hinge system

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Bedroom – Blum hinge system

  • The carpenter is doing the final touch up of the custom made wardrobe.
  • Blum hinge system is used to ensure the doors are closed silently and effortlessly.  Blum is the leading brand that provides accessories for furnitures and cabinets makers.

Master Toilet

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Toilet – Vanity Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Toilet – Vanity

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Toilet – Shower area

Information about the Interior Designer:

Interior Designer Ben Ng

Name: Ben Ng

Experiences: working as a Interior Designer since 2006

Mobile: 9746 2581

Company: BEHome Design Concept

Website: http://www.behomedc.com/index.htm

Also see here for another of his master piece.

Do mentioned that you viewed his works on Vincent Interior Blog for attractive discounts or free gifts!